Seattle Hill traffic light proceeds, park renovation to begin
Seattle Hill Road Traffic Signal - During the week of April 13th, each corner was prepped and graded for new curb and sidewalk. New concrete curbs were poured on Tuesday, and sidewalk may be poured on Friday or early next week, weather dependent. The electrical subcontractor continued with site clean up and installed all ground level junction boxes.

Highland Park Renovation - The first phase of Highland Park renovation will begin on Monday, April 20th with the construction / installation of a sub-drain system to pick up ground water and dry up the soggy grass areas.